Support a space for learning, events, and community – be a part of this impactful project.
Every brick you fund builds a world of knowledge
Why an Auditorium?
To accommodate educational programs, seminars, student activities, and special functions, Dheeniyya Arabic College plans to construct a modern auditorium on the 3rd floor. This space will enrich the learning environment and strengthen community engagement.

We invite your support to make this important addition a reality.
Construction Cost Breakdown
Our projected expenses for the auditorium are listed below
Preliminaries: 462,500.00
Rectification Work : 185,000.00
Concrete Wor 663,725.21
Masonery Work: 1,264,150.00
Roof & Ceiling Work: 1,857,335.00
Floor Wall & Ceiling Finishes: 2,752,805.00
Joinery Work: 2,184,925.00
Plumbing Work: 1,061,400.00
Electrical Work: 648,850.00
Painting Work: 966,935.00
Total Cost: 12,047,625.20
Cleaning of Site: 25,000.00
Breaking of existing balcony walls as per the instructions given by the Engineer to reduce the weight, Rate including for carting away all debris.
In first floor: 45,000.00
In Second floor: 45,000.00
In Third floor: 45,000.00
Removing of existing water tank placed in 3rd floor. Rate including for Breaking & Removing of existing concrete platform: 22,500.00
Chipping of existing floor & preparing for tiling work. Rate including for carting away all debris (2100 Sq.ft): 105,000.00
Removing of existing asbestos roofing sheets & preparing for modification of roof trusses as per engineer detail: 45,000.00
Charges for installation of temporary hoist machine for all lifting work: 60,000.00
Charges for irruption of required scaffolding rate including for all scaffolding materials: 70,000.00
Total: 462,500.00
Repairing & Rectification of Existing Cracks & damages in existing 3rd floor slab. Rate including for Chipping & Removing of damaged area, wire brushing & cleaning of exposed steel reinforcement, Applying of anticorrosive paint for the reinforcement, applying bonding agent, replastering & Making good (Refer Engineers Specifications): Rs. 80,000.00
Repairing & Rectification of Existing Cracks & damages in Stairway Ground floor to third floor. Rate including for Chipping & Removing of damaged area, wire brushing & cleaning of exposed steel reinforcement, Applying of anticorrosive paint for the reinforcement, applying bonding agent, replastering & Making good (Refer Engineers Specifications): Rs.105,000.00
Total Cost: Rs. 185,000.00
Concreting of Beams & Lintols: Rs. 194,287.50
Concreting of water tank Slab: Rs. 55,440.00
Form Work
Form Work of Beams, Slab & Lintols: Rs.164,298.00
Reinforcement Work
In Beams, Slab & Lintils: Rs. 249,699.71
Total Cost: Rs. 663,725.21
9″ thick Brick work in 1:5 cement and sand motor: Rs. 1,048,775.00
4 1/2″ thick Brick work in 1:5 cement and sand motor: Rs.215,375.00
Total Cost: Rs. 1,264,150.00
Supply & Fixing 4″ x 2″ G. I box bar purling. Rate including for applying one coat of oil primer paint and two coats of anticorrosive paint: Rs.273,275.00
Existing Trusses to be modified according to the Engineer’s requirement. Rate including for removing and refixing if necessary and painting. (Provisional Sum): Rs.560,000.00
Supply & Fixing corrugated Asbestos roofing sheets using existing sheets. Rate including for supplying extra sheets required, J bolts and all accessories: Rs.272,000.00
Supply & Fixing of G.I. Valance Board: Rs.152,600.00
Supply & Fixing of G.I. Gutter: Rs.113,900.00
4″ dia PVC Down pipe: Rs.120,400.00
Supply & Fixing of G.I. Bath Flashing: Rs.58,800.00
Supply & Fixing of Asbestos Ridge Tiles: Rs.18360.00
Total Cost: 1,857,335.00
5 /8^ prime prime thick Internal Plastering in 1:1:5 cement, lime & sand mortar finish smooth with neat lime
In walls: Rs.674,505.00
Soffit of slab: Rs.60,480.00
Rendering of Water tank slab: Rs.25,200.00
5 /8^ prime prime thick External Plastering in 1:1:5 cement, lime & sand mortar finish semi rough: Rs.395,200.00
Laying of approved size ceramic floor tiles of approved colour including 1 /2^ prime prime thick screed backing (cement & sand 1:3) point with tile grout to mach: Rs.1,160,530.00
Laying of approved size Glazed ceramic Floor tiles of approved colour including 1 /2^ prime prime thick plaster backing (cement & sand 1:3) point with tile grout to mach.
In toilets height 8′ -0^ prime prime: Rs.100,890.00
Laying of approved size Glazed ceramic wall tiles of approved colour including 1 /2^ prime prime thick plaster backing (cement & sand 1:3) point with tile grout to mach.
In toilets height 8′ -0^ prime prime: Rs.336,000.00
Total Cost: Rs.2,752,805.00
Supply & Fixing of Aluminum Sliding Doors with 80mm sections, as per the details given: Rs.283,200.00
Supply & Fixing of Aluminum Sliding Window with 80mm sections, as per the details given: Rs.531,000.00
Supply & Fixing of Aluminum Door with 100mm sections, as per the details given: Rs.285,600.00
Supply & Fixing of Aluminum Doors for the Toilets: Rs.137,500.00
Supply & Fixing of Aluminum Fanlights in Toilets 2′-0″ x 3′-0″: Rs.135,000.00
Supply & Fixing of G.I box bar Hand Rails as per the draings
(a) First Floor: Rs.270,875.00
(b) Second Floor: Rs.270,875.00
(c) Thired Floor: Rs.270,875.00
Total Cost: 2,184,925.00
Sanitary Fittings
Supply & Fixing of Commode complete with all fittings and Magic bend connected to sewer piping: Rs.120,000.00
Supply & Fixing of Squatting Pan complete with all fittings: Rs.40,000.00
Supply & Fixing of Wash basin: Rs.30,000.00
Supply & Fixing of Wash basin Tap: Rs.6,000.00
Supply & Fixing of Bib Taps: Rs.49,500.00
Supply & Fixing of Bidet Spray: Rs.27,500.00
Supply & Fixing of Angle Valves: Rs.24,000.00
Fixing of S/S Gully Cover: Rs.15,000.00
Water Supply System Cold Water Piping
Supply & Laying 3/4″ dia. PVC piping. Rate shall include for all fittings and accessories: Rs.19,250.00
Supply & Laying 1″ dia. PVC piping. Rate shall include for all fittings and accessories: Rs.29,250.00
Supply & Laying 1″ dia. PVC piping from pump room to water tank. Rate shall include for all fittings and accessories and Clipping with G.I Clips. (Supply Riser & Pump suction line from well): Rs.110,500.00
Supply & Laying 1 1/4″ dia. PVC piping from water tank to 3rd floor. Rate shall include for all fittings. accessories and Clipping with G.I Clips. (Supply Riser): Rs.40,800.00
Supply & Fixing of Gate Valve. Rate Including for all Fittings & Labour.
a) 3/4″ In Bathrooms Externally: Rs.4,000.00
b) 1 1/4″ to Supply Line Externally: Rs.2,600.00
Supply & Fixing of 2000 lit Water Tank. Rate shall included for all fittings and accessories: Rs.80,000.00
Supply & Fixing of 1 HP water Pump. Rate shall included for all fittings and accessories: Rs.105.000.00
DRAINAGE SYSTEM
4″ Dia PVC Riser Pipe Clip to the wall with Brackets. Excluding Fittings.
(a) Ground Floor to Third Floor: Rs.133,200.00
2″ Dia Waste Line Riser. Rate Including for Clipping on Wall & Labour.
(a) First Floor to second floor: Rs.99,000.00
Supply & Fixing of 4″ Gully trap in bathrooms: Rs.12,000.00
1 1/4″ Waste line in bathroom: Rs.15,200.00
Water Proofing of Bathrooms: Rs.63,800.00
Water Proofing of Water Tank: Rs.34,800.00
Total Cost: Rs.1,061,400.00
Light Points
Wiring of Light points with 1044 Copper Cables. Rate including for Required conduiting, cutting the Walls, embedding and all materials and Labour: Rs.240,500.00
2 Way Light Points
Wiring of 2 Way Light points with 1044 Copper Cables. Rate including for Required conduiting, cutting the Walls and embedding and all materials and Labour: Rs.16,000.00
Fan points
Wiring of Fan Points with 1044 Copper Cables and 2.5mm Earth Wire. Rate including for Required conduiting, cutting the walls and embedding and all materials and Labour: Rs.80,000.00
13Amp Plug Points
Wiring of 13 Amp Plug Points with 2.5mm Copper cables & 2.5mm Earth wire. Rate including for Required conduiting, cutting the Walls and embedding and all materials and Labour: Rs.174,000.00
15Amp Plug Points
Wiring of 15 Amp Plug Points with 2.5mm Copper cables & 2.5mm Earth wire. Rate including for Required conduiting, cutting the Walls and embedding and all materials and Labour: Rs.20,000.00
Antenna Points
Wiring with approved Quality Antenna wire. Rate including for conduiting and Labour:
Sub Distribution Board Third Floor
Sub Distribution Board with all accessories wiring and labour. Rate including for
1. 600 x 500 x 200 Metal Enclosure and accessories.
2. 01 Nos 02 Pole MCB.
3. 04 Nos 02 Pole RCCB.
4. 39 Nos Single Pole MCB. Rs.98,500.00
Main Wiring
Wiring of 6mm Main Cable. From MDB to ground floor SDB Rate including for all Conduiting, Fittings and Labour: Rs.14,850.00
Conduiting of Concrete Slab
Rate including for All Conduit, Fittings, J Box, Regiform and Labour. Third floor slab: Rs.5,000.00
Total Cost: Rs.648,850.00
Prepare and Apply 02 Coats of emulsion paint on Internal Walls. Rate shall include for 02 Coats of putty & wall filler: Rs.570,735.00
Prepare and Apply 02 Coats of Weather Shield paint on External walls. Rate shall include for One Coat of Filler: Rs.345,800.00
Prepare and applying 02 Coats of Emulsion paint to internal soffit of slab & Beams. Rate shall include for applying two coats of putty and 1 coat of filler: Rs.50,400.00
Total Cost: Rs.966,935.00